Construction Update Blog 5/2/24

Racking, post installation, and drilling continue on site. Module unloading will also continue over the next few weeks, and silt fence repairs are being made as needed.

Construction Update Blog 4/19/24

Continued work on site includes pre-drilling, pile installation, installing the racking system, excavating for inverter pads, and repairing silt fences as needed. Continue reading

Construction Update 4/05/24

Array grading is complete, and racking system installation has begun. Inverter pad excavation is scheduled to begin next week, and module installation and substation grading are scheduled to begin the following week

Construction Update Blog 3/22/24

Post installation, racking, and compacting are ongoing. Module and wire unloading continue, and substation construction is expected to begin in early April. Over the weekend of March 30, aerial seeding, a chemical-free method of seeding, will occur.  Continue reading

Construction Update Blog 3/8/24

Wire delivery is complete and racking system installation has started. Module unloading continues, and AC routing is expected to begin in the coming weeks.

Construction Update Blog 2/23/24

Array grading and laydown yards are complete. Module unloading, pre-drilling, and compaction continue on-site. Electrical wire deliveries will continue over the next few weeks. In March, AC routing, racking, and module installation will begin. Continue reading

Construction Update 2/9/24

Access road maintenance and rock removal from the construction site have started. Silt fence repairs, module unloading, and pile installation continue. Geotech for the substation is complete. 

Construction Update 1/26/24

Permanent fences will start being installed in early February. Both laydown yards and array grading are complete. Post installation and wire unloading continues, and electrical materials are being delivered in the coming weeks.

Construction Update 1/12/24

Post installation, unloading, and hole drilling continues. Silt fence repairs are continuing as needed. Deliveries have started for electrical material, and unloading will begin soon. Array grading will be completed in the coming weeks. Continue reading

Construction Update 12/29/23

Pile installation and pre-drilling continue. Module deliveries will begin mid-next week.