Construction Update Blog 2/7/24

Substation testing and DC terminations in combiner boxes continue. Workers also continue to address improvements to access roads, egress points, and BMPs on site. Continue reading

Construction Update Blog 1/24/24

Site condition improvements have been completed, including soil stabilization and access road and entrance remediation. Substation testing and medium voltage terminations have resumed.

Construction Update Blog 1/10/24

Access roads are nearly finished, with expected completion by the end of the month. Continued on-site activities include monitoring, maintenance, array seeding, and stabilization. Continue reading

Construction Update Blog 12/13/24

Wire management and cable terminations continue on site. In the next few weeks, access roads will be getting resurfaced to project specifications.

Construction Update Blog 11/29/24

Ongoing work on site includes wire management, general maintenance, and winding tests for inverters. Substation yard lighting installation starts next week.

Construction Update Blog 11/15/24

At the substation, below-grade installation is complete, and bus installation is starting. This month, the site team will begin testing the inverters. Dust control and road maintenance continue throughout the site.

Construction Update Blog 11/1/24

Starting on November 3, crews will work every other Sunday between 9 a.m. and 3 p.m. Spot seeding is near completion, and continued work onsite includes dust control, road maintenance, and electrical system testing. Fiber installation will begin next week.

Construction Update Blog 10/18/24

Substation work continues in the coming weeks, including setting the steel structure, cabling, and installing the disconnect switch and underground conduit. Other continued work on site includes dust control, access road maintenance, and wire management.

Construction Update Blog 10/04/24

Perimeter fence installation, wire management, and mowing continue on site. Substation steel erection begins this week, and the ground grid for the substation is complete. Continue reading

Construction Update Blog 9/20/24

Module installation is nearly complete. Access road repairs and fence installation continues. In the coming weeks, setup for inverter placement and the substation BOXBAY structure will begin.