Construction Update Blog 11/29/24
Ongoing work on site includes wire management, general maintenance, and winding tests for inverters. Substation yard lighting installation starts next week.
Construction Update Blog 11/15/24
At the substation, below-grade installation is complete, and bus installation is starting. This month, the site team will begin testing the inverters. Dust control and road maintenance continue throughout the site.
Construction Update Blog 11/1/24
Starting on November 3, crews will work every other Sunday between 9 a.m. and 3 p.m. Spot seeding is near completion, and continued work onsite includes dust control, road maintenance, and electrical system testing. Fiber installation will begin next week.
Construction Update Blog 10/18/24
Substation work continues in the coming weeks, including setting the steel structure, cabling, and installing the disconnect switch and underground conduit. Other continued work on site includes dust control, access road maintenance, and wire management.
Construction Update Blog 10/04/24
Perimeter fence installation, wire management, and mowing continue on site. Substation steel erection begins this week, and the ground grid for the substation is complete.
Continue reading
Construction Update Blog 9/20/24
Module installation is nearly complete. Access road repairs and fence installation continues. In the coming weeks, setup for inverter placement and the substation BOXBAY structure will begin.
Construction Update Blog 9/6/24
Installation of modules, medium-voltage (MV) cable, and substation below-grade infrastructure continues. Equipment for transmission structure installation is being mobilized to the site. Cable terminations will begin soon.
Construction Update Blog 8/23/24
This week, crews started installing the perimeter fence. Spraying for weeds, mowing, and concrete pouring will continue over the next few weeks. Module installation and racking will be completed soon.
Construction Update Blog 8/9/24
The Main Power Transformer has arrived on site. Perimeter fence work continues, as does module installation. The concrete for PCS foundations has begun to be placed. Vegetation maintenance continues throughout the site.
Construction Update Blog 7/26/24
Module and racking installation continue. The main power transformer will arrive soon and is expected to be pad-mounted at the end of next week. MV and DC collection are ongoing. Inverter foundations continue to be installed to facilitate inverter delivery in the next two weeks.