Construction Update Blog 4/18/25

Continued on-site activities include grading, perimeter fence work, and rack installation. Continue reading

Construction Update Blog 4/4/25

MET station installation has begun, and tracker bonding, perimeter fencing, and medium voltage cable installation continues on site.

Construction Update Blog 3/21/24

Site road enhancements are ongoing. Crews are currently conducting electrical testing in preparation for commissioning. Continued work on site includes perimeter fencing and MV cable installation.

Construction Update Blog 3/7/2025

Substation commissioning has started. Continued activities on site include module installation, perimeter fencing, tracker bonding, and cable installation. 

Construction Update Blog 2/21/24

Substation testing is complete, and the team is currently planning energization. Grounding and perimeter fencing will be completed in the next few weeks.

Construction Update Blog 2/7/24

Substation testing and DC terminations in combiner boxes continue. Workers also continue to address improvements to access roads, egress points, and BMPs on site. Continue reading

Construction Update Blog 1/24/24

Site condition improvements have been completed, including soil stabilization and access road and entrance remediation. Substation testing and medium voltage terminations have resumed.

Construction Update Blog 1/10/24

Access roads are nearly finished, with expected completion by the end of the month. Continued on-site activities include monitoring, maintenance, array seeding, and stabilization. Continue reading

Construction Update Blog 12/13/24

Wire management and cable terminations continue on site. In the next few weeks, access roads will be getting resurfaced to project specifications.

Construction Update Blog 11/29/24

Ongoing work on site includes wire management, general maintenance, and winding tests for inverters. Substation yard lighting installation starts next week.