Construction Update Blog 9/20/24

Module installation is nearly complete. Access road repairs and fence installation continues. In the coming weeks, setup for inverter placement and the substation BOXBAY structure will begin.

Construction Update Blog 9/6/24

Installation of modules, medium-voltage (MV) cable, and substation below-grade infrastructure continues. Equipment for transmission structure installation is being mobilized to the site. Cable terminations will begin soon.

Construction Update Blog 8/23/24

This week, crews started installing the perimeter fence. Spraying for weeds, mowing, and concrete pouring will continue over the next few weeks. Module installation and racking will be completed soon.

Construction Update Blog 8/9/24

The Main Power Transformer has arrived on site. Perimeter fence work continues, as does module installation. The concrete for PCS foundations has begun to be placed. Vegetation maintenance continues throughout the site.

Construction Update Blog 7/26/24

Module and racking installation continue. The main power transformer will arrive soon and is expected to be pad-mounted at the end of next week. MV and DC collection are ongoing. Inverter foundations continue to be installed to facilitate inverter delivery in the next two weeks.

Construction Update Blog 7/12/24

Vegetation management is ongoing. Racking and module installation continue. The GSU/MPT is scheduled for delivery and dress-out this month. Collection cable continues to be installed, and module skip stringing will follow module installation. Continue reading

Construction Update Blog 6/28/24

Post installation is 100% complete on site. Combiner box installation and racking continue, and node installation started this week.

Construction Update Blog 6/14/24

Post installation is nearing completion. Cable, module, and combiner box installation continue on site, as does racking. Inverter foundation installation will begin in the coming weeks. The substation foundations have been placed.

Construction Update Blog 5/31/24

Pre-drilling and pile installation is nearly complete. Substation foundation installations have begun. Collection installation, fence install, racking, and module installation are continuing as scheduled.

Construction Update Blog 5/17/24

Pile installation will be complete in the coming weeks, and collection cable installation has started. Substation site work has begun, and racking and module installation have increased pace. Continue reading