Construction Update Blog 6/13/25
Partial discharge (PD) testing and cold commissioning of the inverters have been completed. I-V curve testing, which evaluates the electrical performance of the solar panels, is currently underway. Remediation work on the combiner boxes (CBXs) has begun.
Construction Update Blog 5/30/25
Albedo sensor installation is complete. I-V Curve trace testing and PD testing continue on site. Substation energization is in progress.
Construction Update Blog 5/16/2025
The site team is wrapping up collection system testing, substation energization, and perimeter fence installation over the next month. New activities include inverter pre-commissioning, energization, and commissioning of the PV arrays.
Construction Update Blog 5/2/25
Excess excavation material has been removed from the site, and crews are installing the final solar panels. In the next few weeks, electrical testing will begin.
Construction Update Blog 4/18/25
Continued on-site activities include grading, perimeter fence work, and rack installation.
Continue reading
Construction Update Blog 4/4/25
MET station installation has begun, and tracker bonding, perimeter fencing, and medium voltage cable installation continues on site.
Construction Update Blog 3/21/24
Site road enhancements are ongoing. Crews are currently conducting electrical testing in preparation for commissioning. Continued work on site includes perimeter fencing and MV cable installation.
Construction Update Blog 3/7/2025
Substation commissioning has started. Continued activities on site include module installation, perimeter fencing, tracker bonding, and cable installation.
Construction Update Blog 2/21/24
Substation testing is complete, and the team is currently planning energization. Grounding and perimeter fencing will be completed in the next few weeks.
Construction Update Blog 2/7/24
Substation testing and DC terminations in combiner boxes continue. Workers also continue to address improvements to access roads, egress points, and BMPs on site.
Continue reading