Construction Update Blog 7/25/2025

Circuit energization and hot commissioning of the inverters continue on-site. Configuration of the SCADA system began this week and will continue in the following weeks. Stormwater Pollution Prevention Plan (SWPPP) monitoring and noxious weed remediation efforts are ongoing. Functional and performance testing will begin soon.

Construction Update Blog 7/11/2025

All medium-voltage alternating current (MVAC) circuit testing has been completed. Inverter inspections and preparations for the remaining circuit energizations are ongoing. Hot commissioning is set to begin soon and will continue over the coming weeks. Availability and capacity testing will follow immediately after.

Construction Update Blog 6/27/25

Open-circuit voltage (VOC) testing is underway, and fusing operations have begun on site. All terminations at the combiner boxes are complete, and installation of the drain tile system is ongoing.

Construction Update Blog 6/13/25

Partial discharge (PD) testing and cold commissioning of the inverters have been completed. I-V curve testing, which evaluates the electrical performance of the solar panels, is currently underway. Remediation work on the combiner boxes (CBXs) has begun.

Construction Update Blog 5/30/25

Albedo sensor installation is complete. I-V Curve trace testing and PD testing continue on site. Substation energization is in progress.

Construction Update Blog 5/16/2025

The site team is wrapping up collection system testing, substation energization, and perimeter fence installation over the next month. New activities include inverter pre-commissioning, energization, and commissioning of the PV arrays.

Construction Update Blog 5/2/25

Excess excavation material has been removed from the site, and crews are installing the final solar panels. In the next few weeks, electrical testing will begin.

Construction Update Blog 4/18/25

Continued on-site activities include grading, perimeter fence work, and rack installation. Continue reading

Construction Update Blog 4/4/25

MET station installation has begun, and tracker bonding, perimeter fencing, and medium voltage cable installation continues on site.

Construction Update Blog 3/21/24

Site road enhancements are ongoing. Crews are currently conducting electrical testing in preparation for commissioning. Continued work on site includes perimeter fencing and MV cable installation.