Performance and capacity testing is ongoing across the site. Vegetation management—including landscape screening—is scheduled to begin in the coming weeks.
The concrete pad for the Operations and Maintenance (O&M) building has been poured, with structural assembly expected to begin within the next three weeks. Noxious weed spraying begins this week, along with continued mowing efforts.