Construction Update 12/29/23
Pile installation and pre-drilling continue. Module deliveries will begin mid-next week.
Construction Update 12/15/23
The laydown yard on Highway 269 is complete. Temporary construction offices will be set up in the coming weeks. Pile installation has begun, and pre-drilling for piles continues. Module deliveries will begin soon after the start of the new year.
Construction Update 12/1/23
Post unloading and pre-drilling started this week. Crews are graveling the laydown yard and installing additional hardware. Array grading continues and silt fence repairs will continue on an as-needed basis. Pile installation will begin next week.
Construction Update 11/17/23
Tree chipping has neared completion, and any remaining piles will be moved offsite in the coming days. All construction entrances are now in place, and the laydown yard at 8409 SR 269 is expected to be complete by the end of the month. Predrilling will begin next week, and pile installation will commence at the beginning of December.
Construction Update 11/3/23
This week, continued efforts include access road installation as well as tree chipping and hauling offsite. The silt fence has been completed; repairs will be made as needed moving forward. Entrances D and F are also complete.
Construction Update 10/20/23
This week, continued efforts include access road installation, array grading, silt fence installation and repair, and laydown yards. Further mobilization is slated to start next week. In the coming weeks, project signage will be placed in various locations, and pre-drilling for piles will begin.
Construction Update 10/6/2023
This week, job trailers will arrive on site. Crews will continue array grading, installing access roads and laydown yards, and installing Stormwater Pollution Prevention Plan (SWPPP) measures.
Construction Update 9/22/2023
This week, installation of the Stormwater Pollution Prevention Plan (SWPPP) measures began. Work will continue on site entrances and the access road to the laydown yard over the next few weeks.
Construction Update 9/8/2023
Survey crews have started prep work around site entrances and the laydown yard. Over the next few weeks, entrances will be installed near 269 and Portland, as well as on Strecker west of 269. Work on the access road to the laydown yard will continue during this time.
In mid- and late September, Stormwater Pollution Prevention Plan (SWPPP) measures will begin onsite, including installation. Civil activities will continue.
Construction Begins
Construction has started! Over the next few weeks, you may see construction traffic as crews start clearing and grubbing the site. In early September, workers will install the site entrances on 269 and Portland, and one on Strecker, West of 269.